What’s upcoming · no promised dates
Alpha state
Current Axiom alpha status, the work blocking qualification, and the engineering phases ahead.
Alpha, not production-ready. The latest hosted Linux resource gate fails both paper modes. Multilevel runs out of memory during million-vertex startup under a 512 MiB address-space cap. Basic completes one million updates and a backup, but runs out of memory during disk-pressure recovery. The 10k durable-updates/s target and billion-vertex capacity are not established.
What the team is working toward
First make the current two-mode product bounded and recoverable at its declared scale. Then broaden adversarial qualification and complete the durable user-facing contracts. No calendar dates are attached: a phase advances only when its evidence passes.
Make the engines fit and recover
Reduce Basic/Multilevel memory peaks, eliminate avoidable graph-sized work, and pass constrained startup, update, backup, pressure, and replay tests before claiming scale.
Strengthen the durable user contract
Qualify external-ID recovery and lifecycle rules; stress atomic batches and version-coherent query snapshots under load, failure, and bounded-resource conditions.
Build application-facing capabilities
Add bipartite constraints, bounded versioned events, stable observability, deterministic replay/history, and factual matching explanations. Introduce transport only after local semantics are qualified.
Gate releases on evidence
Verify reproducible packages and independent research, durability, performance, and deployment gates for each matcher mode. Keep weighted/maximum/capacity matching as separate future engines.
Qualification before expansion
- Pass the 512 MiB / 192 MiB hosted resource envelope for both Basic and Multilevel, including recovery—not only update throughput.
- Repeat uniform, skewed, burst, overload, rollback, and restart workloads; retain latency, memory, storage, and deterministic-state evidence.
- Publish each mode’s actual limits. Do not transfer removed native-engine benchmarks or guarantees to the paper modes.
Hardware power-loss qualification is deferred for this version. Maximum-cardinality, weighted, preference, and capacity matching are separate future-engine questions, not promises in this alpha.